Official State paperwork: https://www.pacodeandbulletin.gov/Display/pacode?file=/secure/pacode/data/052/chapter57/subchapGtoc.html&d=reduce

 

1st step - prospecting land for transmission lines

  • PPL hand delivers or mails a packet stating they are seeking a right-of way

  • PPL is essentially "prospecting" before it applies to the Public Utilities Commission (PUC); it will try to get voluntary right-of-way agreements. They may even attempt to buy your whole land (house and all). PPL cannot condemn a building or a house, but they can try to buy it. They may try this before even applying to the PUC. No utility can take your house or the "reasonable curtilage (100 meters)," which is the space around your dwelling unit. 

  • Landowners may choose to talk, or to not talk, to Land Agents. 

  • Landowners may contact the OCA regarding concerns/their rights about Land Agents 

  • If negotiating, it is recommended to have a lawyer or real estate agent help you. Take your time, and consider all the aspects of it.

  • Do your research - consider adding future acceptable uses, vegetation management/herbicides, subleasing, and other language in the right-of-way contract

  • Share knowledge to help our neighbors to NOT be taken advantage of

  • PPL is required by law to give you a 10-day notice to enter your property.

  • This is the time to raise concerns: The cost & need for the project, safety & health concerns, effects on the environment & the community, and effects on your individual property. Consider other alternatives.
     

2nd Step - application to the Public Utilities Commission (PUC)

  • Application must happen first. Then there are proceedings with the PUC that can take months or years before approval is granted.
    An application submitted to the PUC is NOT the same as PUC approval.

  • PPL will continue to negotiate with landowners up until there is a final PUC order - whether it is PUC approval, or PUC denial of PPL's application.

  • Once PPL has submitted its application to the PUC, PPL will then give the landowners a copy of the file. Landowners will also be notified of PUC’s review of the application submitted by PPL.

  • OCA can now get involved in specific transmission line applications.

  • There will be public input hearings before judges, where landowners are encouraged to make their case and state their concerns.

  • This is the time to really protest.
     

3rd Step - The application is approved OR denied by the Public Utilities Commission (PUC)

  • Before a public utility can build a line, it must have approval of an application from the PUC.

  • If the application is approved, eminent domain will go into effect and the time to negotiate is essentially over.

  • If the PUC approves the PPL application and anyone disagrees, you can then appeal to the Commonwealth Court of PA. The Commonwealth Court MUST take up the appeal. If you are not satisfied with that decision, you can file to the State Supreme Court. The Supreme Court does not have to take up your case.

  • If the PUC DENIES the application submitted by PPL, then it is over. Landowners keep their land, and the transmission line project is shut down.

Transmission Line

Projects

Known

1st
How is a Transmission Line "born" 

Projects below are what we are aware of as of June 2026. If you know of more or have more information, please email beautiful_perry@tutamail.com

Information provided by the
Pennsylvania Office of Consumer Advocate (OCA) 
555 Walnut Street · 5th Floor Forum Place
Harrisburg, PA 17101-1923
Email: consumer@paoca.org
Toll Free: (800) 684-6560

https://www.oca.pa.gov/

Not sure if your line has been
approved by the Public Utilities Commission (PUC)?

Check to see if your letter has a docket number.
If so, then go to this site:

https://www.puc.pa.gov/search/docket-search/ 

If there is NO DOCKET NUMBER then your line application has NOT been submitted yet and you are at stage one. 

If you feel as if your rights are being violated by PPL and/or their contracted land agents, please contact the PA Office of Consumer Advocates (OCA).

 

Below is a power point of a presentation they shared with our group June 20, 2026. 

Screenshot 2026-04-30 203115.png

Juniata - Bernheisel

  • 500 kilovolt transmission line (kV)

  • PPL

  • in the planning stage

  • 13 miles = 68,640’
    Assumed 100’ ROW, added
    If approved: additional 157.57 acres

The Juniata-Bernheisel project is slated to include construction of a new 500 kV substation in Carlisle near the existing Juniata-TMI transmission line. It also includes the rebuild of approx. 13 miles of that existing 500 kV line. The existing Juniata-TMI 500 kV line would be rebuilt as a double circuit between the Juniata Substation in New Bloomfield and the new Bernheisel Substation in Carlisle. Those sections of lines being rebuilt are in Perry and Cumberland Counties. 

 

Additionally, to accommodate the 500 kV line rebuild, an approximately two-mile section of the existing Juniata–Shermansdale 69 kV transmission line will be relocated within the existing corridor in Centre Township. 

 

The project is needed to provide power to a customer (data center) in the Carlisle area.

 

No Application has yet been filed with the PUC for this project.

https://www.facebook.com/RepPerryStambaugh/photos/to-improve-power-supply-in-the-carlisle-area-ppl-electric-utilities-has-announce/1011983114275570/

Juniata Sunbury.png

Juniata-Sunbury

  • 500 kilovolt transmission line (kV)

  • PPL

  • in the planning stage

  • 38 miles = 200,640’
    100’ ROW, added
    If approved, additional 460.60 acres

Juniata-Sunbury is a rebuild of approximately 38 miles of 500 kV transmission line in Perry, Juniata, and Snyder Counties to replace the aging transmission structures. PPL is seeking to acquire approximately 100 feet of additional ROW on the eastern side of the existing ROW to allow for the rebuild without taking the current line out of service. No Application has been filed yet. Our current understanding is that an Application will be filed sometime  in 2028.

https://www.pplelectric.com/site/Landing-Pages/Juniata-Sunbury-Project


https://www.pplelectric.com/site/-/media/ppl-jss-app/assets/Home/Landing-Pages/Juniata-Sunbury-Project/Juniata-Sunbury-Project-Fact-Sheet---11-11-2025.pdf


https://www.pjm.com/-/media/DotCom/planning/rtep-dev/expan-plan-process/ferc-order-1000/rtep-proposal-windows/2025-rtep-window-1-redacted-proposals/2025-w1-16.pdf

Screenshot 2026-04-30 202343.png

Juniata-Honey Grove

  • 500 kilovolt transmission line (kV)

  • PPL

  • planning stages

  • 15.5 miles = 81,840’
    250’ ROW, added
    If approved, additional 469.69 acres

Juniata-Honey Grove is a project where PPL is seeking to expand approximately 15.5 miles of an already-existing transmission line right-of-way (ROW) corridor, to the north, for future use. The corridor begins in Centre Township in Perry County, west of PPL Electric’s Juniata Substation, and moves west to the border of State Game Land 088 in Northeast Madison Township, Perry County. The existing corridor currently houses PPL Electric’s Keystone-Juniata 500 kV and Conemaugh-Juniata 500 kV transmission lines. Currently, there are no immediate plans for a transmission project in this corridor. In February 2026, PPL began contacting landowners in Centre Township (not sure about other areas).

Screenshot 2026-03-24 211015.png
  • 765 kilovolt transmission line (kV)

  •  NextEra Energy Transmission and Exelon Corporation

  • If approved,
    222 miles = 1,172,160’
    Assumed 250’ ROW, new
    If approved: additional 6,727.27 acres

Krammer-Juniata

Kammer Juniata Transmission, LLC (KJT) is proposing the construction of a 765 kV transmission line traversing ten counties in Pennsylvania and one county in West Virginia. This line is projected to be 222 miles long, extending from the Kammer substation in West Virginia to the Juniata substation in Pennsylvania, at a projected cost of $1.7 billion. 



https://local21news.com/news/local/220-miles-of-power-lines-in-pennsylvania-west-virginia-project-approved-by-pjm-with-support-from-governor-josh-shapiro-exelon-energy-nextera-energy-pjm-grid-data-centers-perry-county-central-pa-march-2026


https://www.abc27.com/local-news/pennsylvania-regulators-raise-concerns-over-high-voltage-line-that-would-cut-through-state/#:~:text=The%20project%2C%20the%20OCA%20said,all%20regulatory%20hurdles%20are%20cleared.


.https://www.puc.pa.gov/media/3898/ferc_er26-1734_papuc_comments_to_kammer_juniata_formula_rate_040726.pdf
https://www.pjm.com/-/media/DotCom/planning/rtep-dev/expan-plan-process/ferc-order-1000/rtep-proposal-windows/2025-rtep-window-1-redacted-proposals/2025-w1-237.pdf

According to a notice published July 16 in the Federal Register (link below)
 

Department of Energy
Federal Energy Regulatory Commission
ERC intends to conduct a hearing on the Kammer-Juniata Project. The notice indicates interested persons have 21 days (until August 6) to respond by filing a notice of intervention or motion to intervene if they want to be heard.

https://www.federalregister.gov/documents/2026/07/16/2026-14340/kammer-juniata-transmission-llc-notice-of-institution-of-section-206-proceeding-and-refund-effective

The "business" of transmission Lines